Progress Photographs (Jan-June)
15050 Morro Road, Atascadero, CA 93422     (805) 461-1393


JANUARY 11 - SITE LAYOUT


JANUARY 14TH - SEPTIC SYSTEM

JANUARY 19 - PETE ZAHN MASONRY STARTS FOUNDATION

JANUARY 26 -STEWART WARREN DIGS FOOTINGS

WADE HELPS DIRECT STEWART DIG FOOTINGS

JANUARY 31 - SAND SHELTON SHOOTER

FEBRUARY 2 -  INSTALLING GREASE INTERCEPTOR

FEBRUARY 7 - FRED LOGAN VOLUNTEERS TRACTOR

PLUMBING SYSTEM COMPLETE


FEBRUARY 10 - FOUNDATION READY FOR POUR



     FEBRUARY 14  - FINISHERS ON THEIR KNEES



FEBRUARY 18 - METAL FRAMING COMPLETED



MARCH 5 - WALLS AND ROOF  INSTALLED



MARCH 10 - LOWER INSULATION



MARCH 15 TO 24 - INTERIOR FRAMING


MARCH 10 TO 24 - WORKING INSIDE AND OUT

APRIL & MAY - PARKING LOTS, POND FILLED, WINDOW INSTALLED.